About 4.5 lac commuters travel Kolkata Metro Greenline till March since beginning of underwater commercial operation

About 4.5 lac commuters travel Kolkata Metro Greenline till March since beginning of underwater commercial operation

Kolkata, Apr 23 (UNI) Some 4.5 lac commuters have travelled through the underwater stretch of Green Line in 17 days since the
commercial operation began on March 15 connecting this metropolis with Howrah, the other part of River Hooghly, Kolkata Metro Railway source said on Tuesday.
The loco engineering marvel, connecting Esplanade in the eastern part of Hooghly, the hub of this over 300-year-old city with industrial Howrah in the western part, has been a hit from mid-March, barely nine days after Prime Minister Narendra Modi took the maiden ride with the Metro workers and school students on March 6.
Using the interchanging station at Esplanade, passengers from Kavi Subhash, Kalighat, Dum Dum and Dakshineswar have now been easily availing Green Line 2 services to reach places like Howrah, Howrah Maidan and Mahakaran (Writers' Buildings, formerly the state secretariat), Metro Railway spokesman
Kausik Mitra said.
" This interconnection of Blue Line and Green Line has saved the time
of these passengers and also has been offering smooth and hiccup free
services to the passengers coming from the far-flung areas of South
and North 24 Parganas,Hooghly etc. Out of these 4.5 lakh passengers,
2.32 lakh passengers have terminated their journey at Esplanade from
different stations of Blue Line, " he clarified.
In order to make this interchange smoother and more flexible, queue
managers have been installed at Esplanade Metro station to ensure
seamless interchange of
passengers between Old Esplanade station (Blue Line) and New Esplanade
station (Green Line 2).
These allow all passengers to move freely.
Strategic installation of these queue managers has also eliminated the
possibility of mixing Green Line 2 and Blue Line bound passengers.
This along with numerous banners and stickers already put in place
have immensely benefited the passengers to find their suitable
entry/exit points, escalators as well as trains smoothly.
Metro staff
and RPF personnel have been working in tandem to ensure free and fast
interchange of passengers at Esplanade, specially during the peak
hours.
Meanwhile, construction work of the underground Mominpur -Esplanade
stretch of Joka-Esplanade Metro Corridor (Purple Line) got underway.
In order to construct this stretch, a Tunnel Boring Machine (TBM) will
be used to burrow the tunnels, Mitra added.
For tunnelling the first stretch from Kidderpore to Victoria station,
TBM will start working from inside the premises of St. Thomas School
at Khidderpore.
For this, a launching shaft is required whose
construction work at St. Thomas School is going o­n at present.
Once
this work is completed, TBM will start functioning to burrow the
underground tunnels.
The Rail Vikas Nigam Limited (RVNL), the executing agency, has already
got the clearance certificate from West Bengal Forest Department to
plant 145 new trees
at Joka Metro Railway Depot in lieu of 28 trees at the site of
Victoria station.
The RVNL has already planted these trees at Joka
Depot.
At present, this agency is waiting for the NOC from the Forest
Department for transplantation of these 28 trees. It is expected that
this NOC will be obtained shortly.
For construction of Park Street station of this stretch, Calcutta
Police Club, Calcutta Kennel Club and Rajasthan Club will be relocated
temporarily outside the construction zone.
For the normal operation of
these clubs during the construction period, porta-type containers in
the adjacent vacant land will be provided.
Five such containers have
already been installed o­n the adjacent vacant land at Park Street.
Rest of the containers will be installed shortly.
For the construction of Esplanade Metro station, Kolkata Mounted
Police Paddock will be relocated temporarily to Saheed Minar Maidan.
No Objection Certificate from the Defence Authority has already been
obtained.
For the construction of proposed Esplanade station,
Manohardas Tarag at Esplanade will be dewatered to pave the way for
construction of tunnels below it with the help of Cut and Cover
Method. o­nce the construction is over, this famous waterbody of
Kolkata will be reinstated. Public Works Department has already handed
over this waterbody to RVNL for this project.
UNI PC SJC KK

More News

First private medical college of Meghalaya will start to intake students

03 Oct 2024 | 9:12 PM

Shillong, Oct 3 (UNI) Meghalaya’s first private medical college, the PA Sangma International Medical College, will start to intake students from the current academic session.
The Union Ministry of Health and Family Welfare has granted approval to the USTM for the intake of 150 students in an academic year.
However, the National Medical Commission (NMC), the regulatory body for medical education in India, has yet to grant permission to the PA Sangma International Medical College.

see more..

Arunachal: Three arrested for organizing illegal online gambling

03 Oct 2024 | 8:55 PM

Itanagar, Oct 3 (UNI) Arunachal Pradesh Police have arrested three individuals, including a policeman, for their alleged involvement in organizing an illegal online gambling operation, a senior officer said on Thursday.

see more..

Police arrest accused in 2017 murder case after seven years of pursuit

03 Oct 2024 | 8:22 PM

Aizawl, Oct 3: (UNII) In a significant breakthrough, Mizoram Police have apprehended a fugitive Couple accused in a 2017 murder case after a dedicated chase spanning over seven years.

see more..

Rama Devi expresses satisfaction over SC verdict in connection with murder of her husband

03 Oct 2024 | 7:34 PM

Patna, Oct 3 (UNI) Former MP Rama Devi expressed satisfaction over the upholding of a life term for Munna Shukla by the Supreme Court on Thursday in connection with the murder of her husband Brij Bihari Prasad, Science and Technology Minister in Rabri Devi cabinet in 1998 in Bihar.

see more..

Arunachal Dy CM inaugurates students activity centre

03 Oct 2024 | 7:10 PM

Itanagar, Oct 3 (UNI) Arunachal Pradesh Deputy Chief Minister Chowna Mein inaugurated the Students Activity Centre, laid the foundation stone of Buddhist Study Centre, and participated in an interaction session with faculty and students at Rajiv Gandhi University, Rono Hills, Doimukh near here on Thursday.

see more..
image